Latest Activity

Christine Clifford posted a discussion
Tuesday
Yuriko Nakano posted an event

Free event: SWORDS Showcase - Hypnotic Spoken Words from Romania at Barbican Library

March 14, 2024 from 6pm to 7pm
Mar 5
An event by GLE Website Comms Team was featured
Thumbnail

Differently Various Art Exhibition at different spaces

March 5, 2024 to April 7, 2024
Mar 5
GLE Website Comms Team posted an event
Thumbnail

Variously Different Art Exhibition at different spaces

March 5, 2024 to April 7, 2024
Mar 5

Facebook

There are four Golden Lane Estate related facebook accounts and you can follow them here: goldenlaneEC1 

Golden Lane Estate / RCS site 

Save Bernard Morgan House

City of London

COLPAI Project Weekly Work Update – W/C Monday 25 March 2019

Dear Neighbour

Please see below activities relating to the COLPAI Project, which are due to take place from Monday 25 March 2019.  

Monday 25 March - Friday 29 March

Works will include:

  • The breaking of ground floor slabs with an excavator
  • Asbestos monitoring and removal
  • Demolition material being removed from site  
  • Air quality monitoring
  • Environmental monitoring.

Saturday 30 March - Sunday 31 March

  • No works due.

Notable Points

  • The breaking of ground floor slabs will not be carried out during the reduced impact hours.
  • Asbestos removal works are being carried out in-line with guidance from the Health and Safety Executive
  • An environmental air analyst will be present to monitor the site during works.

Deliveries

  • Muck-away lorries.

Non-ISG Works

  • Road sweeper in place to clean the Golden Lane following the muck-away lorries leaving the site.

Working Hours

Monday to Friday 08:00 to 18:00

Saturday 9:00 to 14:00

Consented Reduced Impact Hours

During reduced impact hours, works will still take place on-site, however, works will not involve percussive machinery or other similar construction involving heavy machinery

Monday to Friday 10:00 to 12:00 and 14:00 to 16:00

Noise, dust and vibration monitoring is in place.

For site emergencies, please contact:  

Steven McCarthy, ISG

T: 07825 719 496

Stephen Beattie, ISG

T: 07816 418 156


Following queries regarding ‘reduced impact hours’, the City of London Corporation’s Code of Practice for Deconstruction and Construction Sites states:

Reduced Impact Hours

The City Corporation requires time restrictions on noisy works to reduce noise disturbance to businesses. These times are known as ‘reduced impact hours’ which are:

  • 10:00 - 12:00 (Monday to Friday)
  • 14:00 - 16:00 (Monday to Friday).

‘Reduced impact hours’ are put in place to give nearby commercial occupiers at least 4 hours without noisy working from street and construction sites during the working day. These periods may be subject to variation in particular circumstances, for example during lunchtimes, adjacent to eating places or businesses where the majority of trade is carried out at lunchtimes.

Work outside standard hours and during reduced impact hours

  • Outside ‘standard hours’ and during ‘reduced impact hours’ the following noise generating activities will not usually be permitted where the activities are likely to cause disturbance
  • Cutting using power tools
  • Breaking out using power tools
  • Other noise generating activities, depending on the specific location of site and neighbours.
  • The use of impact fastener
  • The loading of heavy materials
  • Other noisy activities, depending on the specific location of site and neighbours, deemed unacceptable by Environmental Health Officers.

These documents are also available to view on the City Corporations webpage here: https://www.cityoflondon.gov.uk/business/environmental-health/envir... 

And can be downloaded as a PDF here: https://www.cityoflondon.gov.uk/business/environmental-health/envir...