Dear Neighbour
Please see below activities relating to the COLPAI Project, which are due to take place from Monday 17 June 2019.
Monday 17 June- Friday 21 June
Works will include:
Saturday 22 June – Sunday 23 June
Notable Points
CCTV on site
Deliveries
Non-ISG Works
Working Hours
Monday to Friday 08:00 to 18:00
Saturday 9:00 to 14:00
Consented Reduced Impact Hours
During reduced impact hours, works will still take place on-site. However, works will not involve percussive machinery or other similar construction involving heavy machinery.
Monday to Friday 10:00 to 12:00 and 14:00 to 16:00
Noise, dust and vibration monitoring is in place.
For site emergencies, please contact:
Steven McCarthy, ISG
T:07825 719 496
Stephen Beattie, ISG
T: 07816 418 156