Golden Lane Festive Singalong
December 14, 2024 from 3pm to 6pmLaunch of the Golden Lane Bike Project
December 14, 2024 from 2pm to 3pm
There are four Golden Lane Estate related facebook accounts and you can follow them here: goldenlaneEC1
22 discussions
170 discussions
608 discussions
126 discussions
1411 discussions
127 discussions
16 discussions
21 discussions
235 discussions
DETAILS OF WORK | COST TO THE BLOCK | COST TO THE FLAT | |
At Current Prices | At Current Prices | ||
Podium Repairs & Water Proofing | £274,178 |
£1,740 | |
External/Internal Repairs & Redecoration | £157,573 | £1,000 | |
Window Replacement | £11,998,219 | £76,147 | |
Communal Heating Installation | £2,797,594 | £17,755 | |
Roof Renewal | £475,063 | £3,015 | |
Landlords Electrical Remedial Works | £606,907 | £3,852 | |
AGGREGATE AMOUNTS OF ABOVE ESTIMATES | £16,309,534 | £103,509 | |
Tags:
So does the Great Arthur House successful challenge to similar costs affect this ?
Good question. We need to find out. By any chance, do you know when is the next residents meeting?
Sorry no idea.
Is there an agreed percentage contribution from the Leaseholders? It's not so clear from the latest summary.
Another good question. We need to ask City of London about it.
Does anyone know when is the next residents meeting?
GLERA has just been able to confirm next general meeting for Monday 31 October 7 pm downstairs in the Community Centre. Notices will go up next week.
On the meeting minutes from the Residents Liaison Group of the 25th of August there is mention of a published Simplified Cost Document but it is not attached to the published minutes. Did any of the participants get hold of it?
© 2024 Created by GLE Website Comms Team. Powered by