Latest Activity

Jax posted a discussion
16 hours ago
Jax updated an event

Festive tunes and carols in the Park at Fortune Street Park

December 11, 2024 from 5pm to 7:30pm
Nov 20
Shirley posted events
Nov 18
Maria Elizabeth Prior posted a discussion
Nov 16

Facebook

There are four Golden Lane Estate related facebook accounts and you can follow them here: goldenlaneEC1 

Golden Lane Estate / RCS site 

Save Bernard Morgan House

City of London

Forum

HEALTH & WELLBEING

170 discussions

ESTATE OFFICE ANNOUNCEMENTS

608 discussions

GENERAL COMMENTS & QUERIES

1411 discussions

MAJOR WORKS & PROJECTS

127 discussions

COLPAI

Site of former Richard Cloudesley School

168 discussions

BERNARD MORGAN HOUSE

16 discussions

COMMUNITY CENTRE

21 discussions

ITEMS FOR SALE OR RECYCLE

235 discussions

COLPAI Project Weekly Work Update – W/C Monday 15 April 2019

Dear Neighbour

Please see below activities relating to the COLPAI Project, which are due to take place from Monday 15 April 2019.

Monday 15 April - Thursday 18 April

Works will include:

  • Excavator exchange works - The delivery of a replacement excavator engine was due to take place on Saturday 13 April. Following discussion with the City of London Environmental Health Department, the delivery will now take place on Monday 15 April between 6pm - 8pm. The excavator delivery will not involve any traffic disruption and site operatives will be in attendance to oversee the delivery. We will continue to ensure that the impact of these works is kept to a minimum
  • The breaking of ground floor slabs with an excavator
  • Asbestos monitoring and removal
  • Demolition material being removed from site
  • Air quality monitoring
  • Environmental monitoring.

Friday 19 April – Monday 22 April

  • Site is closed for Easter Break.

Notable Points

  • The breaking of ground floor slabs will not be carried out during the reduced impact hours
  • Asbestos removal works are being carried out in-line with guidance from the Health and Safety Executive
  • CCTV on site - For additional security ISG has installed a CCTV monitoring system, which is operated by movement sensors. This system is only active within the site boundary and cannot be directed outside the boundary lines
  • An environmental air analyst will be present to monitor the site during works.

Deliveries

  • Muck-away lorries
  • Excavator exchange works - Monday 15 April between 6pm-8pm.

Non-ISG Works

  • Road sweeper in place to clean Golden Lane following the muck-away lorries leaving the site.

Future Works

  • Future works will include the demolition of the brick wall on the Hatfield House and Baltic Street boundaries. We will provide further updates and information on these works in due course.

Working Hours

Monday to Friday 08:00 to 18:00

Saturday 9:00 to 14:00

Consented Reduced Impact Hours

During reduced impact hours, works will still take place on-site, however, works will not involve percussive machinery or other similar construction involving heavy machinery.

Monday to Friday 10:00 to 12:00 and 14:00 to 16:00

Noise, dust and vibration monitoring is in place.

For site emergencies, please contact:

Steven McCarthy, ISG

T:07825 719 496

Stephen Beattie, ISG

T: 07816 418 156

Views: 64

Reply to This

© 2024   Created by GLE Website Comms Team.   Powered by

Badges  |  Report an Issue  |  Terms of Service