Latest Activity

Jax updated an event

Festive tunes and carols in the Park at Fortune Street Park

December 11, 2024 from 5pm to 7:30pm
Wednesday
Shirley posted events
Nov 18
Maria Elizabeth Prior posted a discussion
Nov 16
Jax posted an event

Festive tunes and carols in the Park at Fortune Street Park

December 11, 2024 from 5pm to 7:30pm
Nov 14

Facebook

There are four Golden Lane Estate related facebook accounts and you can follow them here: goldenlaneEC1 

Golden Lane Estate / RCS site 

Save Bernard Morgan House

City of London

Forum

HEALTH & WELLBEING

170 discussions

ESTATE OFFICE ANNOUNCEMENTS

608 discussions

GENERAL COMMENTS & QUERIES

1411 discussions

MAJOR WORKS & PROJECTS

127 discussions

COLPAI

Site of former Richard Cloudesley School

168 discussions

BERNARD MORGAN HOUSE

16 discussions

COMMUNITY CENTRE

21 discussions

ITEMS FOR SALE OR RECYCLE

235 discussions

COLPAI Project Weekly Work Update – W/C Monday 23 March

Dear Neighbour

To ensure that the school building is delivered on time for the City of London Primary Academy Islington to take possession of the building in December 2020, some weekend works may be necessary. We are writing to you today to inform you that as the COLPAI Project moves into the next phase of construction we will be changing the way we notify you of potential weekend working.

As you will be aware, we avoid working Saturdays when possible, but as we move into a new phase of works it may not always be feasible to include details of weekend working in the weekly notice that is issued. However, if weekend works are to take place, we will be issuing this as a separate notice via email and posting notices in estate noticeboards. We will aim to give a minimum of 24 hours’ notice of weekend works taking place.
 
Any weekend working that does take place will be confined to our agreed 9am to 2pm working hours and will take place on Saturdays only. To ensure that the impact of these works is kept to a minimum the site team will continue to follow our established working practices.
 
Please see below activities relating to the COLPAI Project, which are due to take place from Monday 23 March 2020.
 

Monday 23 March – Friday 27 March
Works will include:

  • Piling operations in the northern section of the residential area
  • Groundworks & concrete pour works for the school first floor and school hall substructure
  • Excavators filling muck away lorries
  • Asbestos watching brief 
  • Air quality monitoring
  • Environmental monitoring

Saturday 28 March & Sunday 29 March

  • TBC

Deliveries

  • Muck-away and stone lorries
  • Pit lane on Golden Lane is now operational for lifting materials by crane into the site.

Notable Points

  • Asbestos removal works are being carried out in-line with guidance from the Health and Safety Executive  
  • An environmental air analyst will be present to monitor the site during works.

On-site security

  • Security guard now on-site full time 7.00am – 6.30pm
  • CCTV security cameras are now monitoring the site 24 hours a day, 7 days a week.

Non-ISG Works

  • Road sweeper in place to clean Golden Lane following the muck-away lorries leaving the site

Working Hours
Monday to Friday 08:00 to 18:00
Saturday 9:00 to 14:00

 
Consented Reduced Impact Hours
During reduced impact hours, works will still take place on-site. However, works will not involve percussive machinery or other similar construction involving heavy machinery.
 
Monday to Friday 10:00 to 12:00 and 14:00 to 16:00
 
Noise, dust and vibration monitoring is in place. 
 
For site emergencies, please contact:
 
Steven McCarthy, ISG
T: 07825 719 496
Stephen Beattie, ISG
T: 07816 418 156

Views: 22

Reply to This

© 2024   Created by GLE Website Comms Team.   Powered by

Badges  |  Report an Issue  |  Terms of Service