Latest Activity

Christine Clifford posted a discussion
Tuesday
Yuriko Nakano posted an event

Free event: SWORDS Showcase - Hypnotic Spoken Words from Romania at Barbican Library

March 14, 2024 from 6pm to 7pm
Mar 5
An event by GLE Website Comms Team was featured
Thumbnail

Differently Various Art Exhibition at different spaces

March 5, 2024 to April 7, 2024
Mar 5
GLE Website Comms Team posted an event
Thumbnail

Variously Different Art Exhibition at different spaces

March 5, 2024 to April 7, 2024
Mar 5

Facebook

There are four Golden Lane Estate related facebook accounts and you can follow them here: goldenlaneEC1 

Golden Lane Estate / RCS site 

Save Bernard Morgan House

City of London

COLPAI Project Weekly Work Update – W/C Monday 23 March

Dear Neighbour

To ensure that the school building is delivered on time for the City of London Primary Academy Islington to take possession of the building in December 2020, some weekend works may be necessary. We are writing to you today to inform you that as the COLPAI Project moves into the next phase of construction we will be changing the way we notify you of potential weekend working.

As you will be aware, we avoid working Saturdays when possible, but as we move into a new phase of works it may not always be feasible to include details of weekend working in the weekly notice that is issued. However, if weekend works are to take place, we will be issuing this as a separate notice via email and posting notices in estate noticeboards. We will aim to give a minimum of 24 hours’ notice of weekend works taking place.
 
Any weekend working that does take place will be confined to our agreed 9am to 2pm working hours and will take place on Saturdays only. To ensure that the impact of these works is kept to a minimum the site team will continue to follow our established working practices.
 
Please see below activities relating to the COLPAI Project, which are due to take place from Monday 23 March 2020.
 

Monday 23 March – Friday 27 March
Works will include:

  • Piling operations in the northern section of the residential area
  • Groundworks & concrete pour works for the school first floor and school hall substructure
  • Excavators filling muck away lorries
  • Asbestos watching brief 
  • Air quality monitoring
  • Environmental monitoring

Saturday 28 March & Sunday 29 March

  • TBC

Deliveries

  • Muck-away and stone lorries
  • Pit lane on Golden Lane is now operational for lifting materials by crane into the site.

Notable Points

  • Asbestos removal works are being carried out in-line with guidance from the Health and Safety Executive  
  • An environmental air analyst will be present to monitor the site during works.

On-site security

  • Security guard now on-site full time 7.00am – 6.30pm
  • CCTV security cameras are now monitoring the site 24 hours a day, 7 days a week.

Non-ISG Works

  • Road sweeper in place to clean Golden Lane following the muck-away lorries leaving the site

Working Hours
Monday to Friday 08:00 to 18:00
Saturday 9:00 to 14:00

 
Consented Reduced Impact Hours
During reduced impact hours, works will still take place on-site. However, works will not involve percussive machinery or other similar construction involving heavy machinery.
 
Monday to Friday 10:00 to 12:00 and 14:00 to 16:00
 
Noise, dust and vibration monitoring is in place. 
 
For site emergencies, please contact:
 
Steven McCarthy, ISG
T: 07825 719 496
Stephen Beattie, ISG
T: 07816 418 156