welcome

The Golden Lane Estate website is run by GLE residents (GLE website comms team) and supported by the Golden Lane Residents' Association.

The forums are moderated.  Any comments which appear to be abusive or potentially libellous or which contravene the terms of service under which the site is licensed by the service provider Ning will be removed. 

Privacy Policy

Forum

MAJOR WORKS & PROJECTS

50 discussions

COLPAI

Site of former Richard Cloudesley School

83 discussions

BERNARD MORGAN HOUSE

16 discussions

COMMENT ON GOLDEN LANE

1172 discussions

COMMUNITY CENTRE

14 discussions

HEALTH & WELLBEING

26 discussions

ESTATE OFFICE ANNOUNCEMENTS

454 discussions

ITEMS FOR SALE OR RECYCLE

181 discussions

COLPAI Project Weekly Work Update – W/C Monday 27 May 2019

Dear Neighbour

Please see below activities relating to the COLPAI Project, which are due to take place from Monday 27 May 2019. 

Monday 27 May

  • Site closed for Bank Holiday.

Tuesday 28 May- Friday 31 May

Works will include:

  • Excavation and removal of obstructions in the ground
  • Asbestos watching brief and removal
  • Demolition material being removed from site
  • Air quality monitoring
  • Environmental monitoring.

Saturday 1 June – Sunday 2 June

  • No works.

Notable Points

  • Asbestos removal works are being carried out in-line with guidance from the Health and Safety Executive
  • An environmental air analyst will be present to monitor the site during works.

CCTV on site

  • For additional security, ISG has installed a CCTV monitoring system. The site is monitored 24 hours a day, seven days a week. This system is only active within the site boundary and cannot be directed outside the boundary lines.

Deliveries

  • Muck-away lorries.

Non-ISG Works

  • Road sweeper in place to clean Golden Lane following the muck-away lorries leaving the site. 

Working Hours

Monday to Friday 08:00 to 18:00

Saturday 9:00 to 14:00 

Consented Reduced Impact Hours

During reduced impact hours, works will still take place on-site, however, works will not involve percussive machinery or other similar construction involving heavy machinery.

Monday to Friday 10:00 to 12:00 and 14:00 to 16:00

Noise, dust and vibration monitoring is in place.

For site emergencies, please contact:

Steven McCarthy, ISG

T: 07825 719 496

Stephen Beattie, ISG

T: 07816 418 156