welcome

The Golden Lane Estate website is run by GLE residents (GLE website comms team) and supported by the Golden Lane Residents' Association.

The forums are moderated.  Any comments which appear to be abusive or potentially libellous or which contravene the terms of service under which the site is licensed by the service provider Ning will be removed. 

Privacy Policy

Forum

MAJOR WORKS & PROJECTS

54 discussions

COLPAI

Site of former Richard Cloudesley School

92 discussions

BERNARD MORGAN HOUSE

16 discussions

GENERAL COMMENTS & QUERIES

1175 discussions

COMMUNITY CENTRE

15 discussions

HEALTH & WELLBEING

27 discussions

ESTATE OFFICE ANNOUNCEMENTS

466 discussions

ITEMS FOR SALE OR RECYCLE

180 discussions

COLPAI Project Weekly Work Update – W/C Monday 6 May 2019

Dear Neighbour

Please see below activities relating to the COLPAI Project, which are due to take place from Monday 6 May 2019.

Monday 6 May

  • Site is closed for Bank Holiday.

Tuesday 7 May- Friday 10 May

Works will include:

  • UKPN connection works along Basterfield Service Road
  • Hoarding removal on Basterfield Service Road
  • Excavating trial inspection pits
  • Breaking out and removal of foundation ground and beams
  • Asbestos watching brief and removal
  • Removal of demolition material from site
  • Air quality monitoring
  • Environmental monitoring.

 Saturday 11 May – Sunday 12 May

  • No works.

Notable Points

  • The breaking of ground floor slabs will not be carried out during the reduced impact hours
  • Asbestos removal works are being carried out in-line with guidance from the Health and Safety Executive
  • An environmental air analyst will be present to monitor the site during works.

CCTV on site

  • For additional security, ISG has installed a CCTV monitoring system. The site is monitored 24 hours a day, seven days a week. This system is only active within the site boundary and cannot be directed outside the boundary lines.

Deliveries

  • Muck-away lorries.

Non-ISG Works

  • Road sweeper in place to clean Golden Lane following the muck-away lorries leaving the site.

Working Hours 

Monday to Friday 08:00 to 18:00

Saturday 9:00 to 14:00

Consented Reduced Impact Hours

During reduced impact hours, works will still take place on-site, however, works will not involve percussive machinery or other similar construction involving heavy machinery.

Monday to Friday 10:00 to 12:00 and 14:00 to 16:00

Noise, dust and vibration monitoring is in place. 

For site emergencies, please contact: 

Steven McCarthy, ISG

T: 07825 719 496

Stephen Beattie, ISG

T: 07816 418 156

Views: 16

Reply to This

© 2019   Created by Paul Lincoln.   Powered by

Badges  |  Report an Issue  |  Terms of Service