welcome

The Golden Lane Estate website is run by GLE residents (GLE website comms team) and supported by the Golden Lane Residents' Association.

The forums are moderated.  Any comments which appear to be abusive or potentially libellous or which contravene the terms of service under which the site is licensed by the service provider Ning will be removed. 

Privacy Policy

Forum

MAJOR WORKS & PROJECTS

50 discussions

COLPAI

Site of former Richard Cloudesley School

83 discussions

BERNARD MORGAN HOUSE

16 discussions

COMMENT ON GOLDEN LANE

1172 discussions

COMMUNITY CENTRE

14 discussions

HEALTH & WELLBEING

26 discussions

ESTATE OFFICE ANNOUNCEMENTS

454 discussions

ITEMS FOR SALE OR RECYCLE

180 discussions

COLPAI Project, Weekly Works Update, w/c Monday 4 February

Dear Neighbour 

Please see below activities relating to the COLPAI Project, which are due to take place from Monday 4 February. 

Monday 4 February - Friday 8 February 

  • Removal of spoil from site.

Saturday 9 February – Sunday 10 February

  • No works due to take place.

Deliveries continue to site in line with the approved logistics plan:

  • UKPS delivery
  • Removal of spoil from site.

Working Hours

Monday to Friday 08:00 to 18:00

Saturday 9:00 to 14:00

Consented quiet times 

Monday to Friday 10:00 to 12:00 and 14:00 to 16:00